JAN 30, 2025
STP PLANT:
The Sewage Treatment Plant (STP) has been successfully installed at Prabh Aasra, marking a key step in improving wastewater management and hygiene at the hospital. With essential components integrated and Kota stone flooring in progress, this advancement will enhance sustainability and support the well-being of residents and patients.

UPS INSTALLED:-The UPS system has been successfully installed at Prabh Aasra’s hospital, ensuring continuous power for critical operations and equipment. A 3 kVA UPS in the reception area further protects front-end services from power disruptions, enhancing overall facility safety and efficiency.

Generator Upgrade to 140 KVA: The hospital's 82 KVA generator has been replaced with a 140 KVA unit to enhance efficiency as the facility expands. This upgrade supports the increasing demand for power, especially with the growing number of surgeries and hospital operations.

CONSTRUCTION PROGRESS UPDATE:- The back side building work is almost completed. Lab area also shifted and new washrooms for Public and Staff are ready.

Pathology Lab Shifting :-
The pathology lab has moved to a larger, upgraded space, allowing advanced equipment installation for improved efficiency, accessibility, and diagnostics.

Detail of Last Three Months Surgeries and Procedures Performed:


MACHINERY REQUIRED AT HOSPITAL:

Updates from 50 Bed Hospital Project’s efforts, posted on a regular basis.